Build or renovate
Official name: Prepare a building project in Vienna
You want to build or renovate in Vienna. Before that, you need to check many things with the authorities. Here you see which steps matter before construction starts.
No account · Answers stay in your browser
- Steps
- 5 key steps, up to 6 depending on your situation
- For you
- 5 short questions, then you see your steps
- Main office
- MA 37 / befugte Planung
- Costs
- none named in the sources
- Online
- possible for 1 of 6 steps
How it works
These are the key steps, in the right order. Answer the short questions; then you see exactly what applies to you and what is added.
Have the right procedure determinedThe procedure type is the route at the office for your building project. For example a Bewilligung, which is a permit. Or an Anzeige, which is a notice.Key step
- Why?
- The type and size of your project decide the route. The documents depend on it too.
- What you do
- Check this with an authorised planner or with MA 37. MA 37 is the building authority in Vienna. This guide does not decide whether you may build.
- Where?
- MA 37 / befugte PlanungDirectly with the named service
In detail
Determine the procedure with qualified support first
Type and extent determine procedure and records. Clarify permit, notification or exceptions with an authorised planner or MA 37. This plan does not decide whether building is permitted.
SourceAllgemeine Baubewilligung: Antrag
Allgemeine Baubewilligung: AntragStadt Wien · MA 37 · retrieved on 09/10/2026
Open original sourceFind an expert to draw the plansAn authorised planner is an expert who may make building plans. For example an architect or a master builder.Key step
- Why?
- They prepare the documents your project needs. Scope and costs depend on the project.
- What you do
- Discuss the current state, the planned changes and technical proof with them. Also check the owners’ consent and who may represent you.
- Where?
- Befugte Planverfasser / MA 37Directly with the named service
In detail
Arrange an authorised planner and project records
Discuss existing conditions, changes and technical evidence with the planner. Clarify owner consent and representation. Scope and costs depend on the project.
SourceNotwendige Unterlagen für eine Baubewilligung
Notwendige Unterlagen für eine BaubewilligungStadt Wien · MA 37 · retrieved on 09/10/2026
Open original sourceFind out which documents to hand inThe submission list shows which documents you must hand in. MA 37 has a list for this.For everyone
- Why?
- Every building project needs different plans and proof. A general template does not replace a check for your project.
- What you do
- Go through the list with your planner. Often included: the Ansuchen um Baubewilligung, which is the application. Also building plans, proof, consent and maybe a power of attorney.
- Where?
- Befugte Planung / MA 37Directly with the named service
What you need
- Building permit application
Document explained
Complete for the procedure clarified with qualified support.
- Requirement
- Check for your case
- Submission format
- Clarify format with the service
- Translation
- No specific rule recorded; clarify foreign-language records with the service.
- Authentication
- No specific rule recorded; clarify need before obtaining records.
- Recency
- No fixed age limit recorded; clarify currency with the service.
SourceNotwendige Unterlagen für eine Baubewilligung
Notwendige Unterlagen für eine BaubewilligungStadt Wien · MA 37 · retrieved on 09/10/2026
Open original source - Building plans and project-specific evidence
Document explained
Have an authorised planner assemble records and clarify required signatures.
- Requirement
- Check for your case
- Submission format
- Clarify format with the service
- Translation
- No specific rule recorded; clarify foreign-language records with the service.
- Authentication
- No specific rule recorded; clarify need before obtaining records.
- Recency
- No fixed age limit recorded; clarify currency with the service.
SourceNotwendige Unterlagen für eine Baubewilligung
Notwendige Unterlagen für eine BaubewilligungStadt Wien · MA 37 · retrieved on 09/10/2026
Open original source - Consent and any representation authority
Document explained · Depends on your case
For another owner’s property clarify appropriate evidence with the planner.
- Requirement
- Check for your case
- Submission format
- Clarify format with the service
- Translation
- No specific rule recorded; clarify foreign-language records with the service.
- Authentication
- No specific rule recorded; clarify need before obtaining records.
- Recency
- No fixed age limit recorded; clarify currency with the service.
SourceNotwendige Unterlagen für eine Baubewilligung
Notwendige Unterlagen für eine BaubewilligungStadt Wien · MA 37 · retrieved on 09/10/2026
Open original source
In detail
Agree the project-specific submission checklist
Use the MA 37 list with your planner. Check the plans, declarations and assessments for your procedure; generic templates do not replace project review.
SourceNotwendige Unterlagen für eine Baubewilligung
Notwendige Unterlagen für eine BaubewilligungStadt Wien · MA 37 · retrieved on 09/10/2026
Open original sourceCheck submission, fees and confirmationSubmitting means you hand in your application at the office. Here you check the route, fees and confirmation.Key step
- Why?
- MA 37 needs complete documents. Submitting does not mean you may start building right away.
- What you do
- Agree the route and documents with MA 37. Keep the confirmation safe. Also keep any requests for more documents.
- Where?
- MA 37Directly with the named service
In detail
Clarify submission, fees and confirmation
Agree submission route and complete records with MA 37. Keep confirmation and evidence requests. Submission alone is not permission to start immediately.
SourceAllgemeine Baubewilligung: Antrag
Allgemeine Baubewilligung: AntragStadt Wien · MA 37 · retrieved on 09/10/2026
Open original sourceCheck requests before you start buildingAfter submitting, there may be requests or a Bescheid. A Bescheid is the written decision from the office.Key step
- Why?
- The decision can contain conditions. Conditions are rules you must follow. Check everything before work starts.
- What you do
- Check the decision, conditions and required notices with your planner. Check dates based on your procedure. No start date is calculated here.
- Where?
- MA 37 / befugte PlanungDirectly with the named service
In detail
Review evidence requests and start conditions
Have the planner review the decision, conditions and necessary notifications before starting. Clarify dates for your procedure; no generic start date is calculated.
SourceAllgemeine Baubewilligung: Antrag
Allgemeine Baubewilligung: AntragStadt Wien · MA 37 · retrieved on 09/10/2026
Open original source
Depending on your situation, this is added
- Prepare the online application
Frequently asked questions
Can I do this online?
1 of 6 possible steps mention an online channel in their text. Requirements are in the official source.
What does it cost?
No costs are recorded for these steps in the linked sources. Fees may still apply.
Do I need an einfach.wien account?
No. The plan works without registration; answers stay in your browser.
Does einfach.wien submit my application?
No. einfach.wien helps you prepare and links official channels. You submit applications yourself to the responsible service.
What this page is based on
The information is based on official sources. einfach.wien is a private project; the content has not been professionally reviewed. All information without guarantee, no legal advice. The responsible office is always authoritative.
SourceAllgemeine Baubewilligung: Antrag
Stadt Wien · MA 37 · retrieved on 09/10/2026
Open original sourceSourceNotwendige Unterlagen für eine Baubewilligung
Stadt Wien · MA 37 · retrieved on 09/10/2026
Open original sourceSourceDigitale Baueinreichung
Stadt Wien · MA 37 · retrieved on 09/10/2026
Open original source